UFC 3-260-11FA
25 May 2005
Table 2-1
RFP Drawings
Information/Guidance
Drawing Description
Nominal
Partial
Full
Criteria
Criteria
Criteria
Cover Sheet
X
X
Location Plan/Project Site Plan
X
X
X
Contractor Access, Storage, and Haul
X
X
X
Routes
Horizontal and Vertical Control
X
X
Existing Topography (if available)
(X)
X
Existing Utilities
X
X
Demolition Plans
X
X
Runway Geometry w/Key Elevations
X
X
X
X
X
X
Typical Pavement Sections
X
X
X
X
X
X
Conceptual Grading Plans
X
Conceptual Jointing Plan
X
Joint/Sealant Detail
X
Grounding Point Locations
X
Mooring Point Locations
X
Pavement Marking Plans
X
Visual Navigation Aids Location
X
Electronic Navigation Aids Location
X
Apron Lighting Plan
X
Electric Vault Location
X
Fire Suppression System Plan
X
2-6
RFP SPECIFICATIONS. Inclusion of edited UFGS in an RFP for airfield
projects is required for either Partial or Full Criteria. See Chapter 4 for additional
information on RFP specifications.
2-7
CONCEPTUAL DESIGN REPORT. Project definition should include a
Government-prepared conceptual design analysis for Partial or Full criteria that
includes:
Design analyses for all designs furnished by the Government, such as
pavement design.
Government-furnished data necessary for the D-B Contractor to further
the design and prepare the final project design analysis.
8