Per Table C-1: 4260 L/m (1125 gpm ) for 90 minutes
(2) Example 2 - Welding Shop (Ordinary Group 1)
Factors
Values
1.
Fire Department response
Off-site (within 3.2 km (2 miles))
2
2.
Type of construction
Type II
3
3.
Number of Stories
Single story
1
4.
Separation Distance
6.1 m (20 ft)
4
5.
Building Floor Area
2044 m2 (22,000 ft2)
3
6.
Firefighting access
76.2 m (250 ft)
4
Total Weighing Value
17
Per Table C-1: 7570 L/m (2000 gpm) for 150 minutes
(1) Example 3 - Barracks (Light Hazard)
Factors
Values
1.
Fire Department response
Off-site (more than 4.8 km (3 miles))
3
2.
Type of construction
Type II
2
3.
Number of Stories
Three stories
3
4.
Separation Distance
12.2 m (40 ft)
2
5.
Building Floor Area
836 m2 (9,000 ft2)
2
6.
Firefighting access
61 m (200 ft)
2
Total Weighing Value
14