PURPOSE AND SCOPE. This UFC is comprised of two sections.
Chapter 1 introduces this UFC. Appendix A contains the full text copy of SECTION 3 of
Military Handbook 1028/1C. This UFC serves as criteria until such time as the full text
UFC is developed from the MIL-HDBK and other sources.
This UFC provides general criteria for the design of passive solar
buildings.
1-2
APPLICABILITY. This UFC applies to all Navy service elements and
Navy contractors.
1-2.1
General Building Requirements. All DoD facilities must comply with
UFC 1-200-01, Design: General Building Requirements. If any conflict occurs between
this UFC and UFC 1-200-01, the requirements of UFC 1-200-01 take precedence.
1-2.2
Safety. All DoD facilities must comply with DODINST 6055.1 and
applicable Occupational Safety and Health Administration (OSHA) safety and health
standards.
NOTE: All NAVY projects, must comply with OPNAVINST 5100.23 (series), Navy
Occupational Safety and Health Program Manual. The most recent publication in this
series can be accessed at the NAVFAC Safety web site:
OPNAVINST 5100.23, the requirements of OPNAVINST 5100.23 take precedence.
1-2.3
Fire Protection. All DoD facilities must comply with UFC 3-600-01,
Design: Fire Protection Engineering for Facilities. If any conflict occurs between this
UFC and UFC 3-600-01, the requirements of UFC 3-600-01 take precedence.
1-2.4
Antiterrorism. All DoD facilities must comply with UFC 4-010-01,
Design: DoD Minimum Antiterrorism Standards for Buildings. If any conflict occurs
between this UFC and UFC 4-010-01, the requirements of UFC 4-010-01 take
precedence.
1-3
Ventilation for Control of Air Contaminants and Flammable Vapors.
Replace sentence two of paragraph 3.4.2 in Appendix A with the following:
The ventilation for the hangar area should furnish 100 percent
filtered outside air at a horizontal laminar flow velocity of 0.68m/s (100
fpm) across the entire cross-section area of the hangar bays for chemical
stripping/painting operations for worker safety and overspray control.
||content||
\ 1-4
Grounding. Delete paragraph 3.5.3 and replace with the following: