UFC 4-390-01
23 July 2003
b) Verify that system drawings, technical manuals, and
operating and emergency procedures reflect the as-built condition
of the system. All required drawings and operating and emergency
procedure revisions should be submitted to the SCA for review and
approval.
c)
Initiate the preventive maintenance plan for the
system.
d)
Request an on-site survey of the system by the SCA.
Upon completion of a successful on-site survey, the SCA will
grant the system a new certification. This procedure applies to
all systems.
26