UFC 3-570-06
JANUARY 31 2003
6. Use AF Form 1687, Leak/Failure Data
Record, as appropriate and forward to the BCCE.
(d) Protective coating corrosion control is by
Service Contract (OPR: Maintenance Engineering):
1.
Update painting records as required.
2. Report any damage found to the BCCE for
subsequent repair or recommendations.
3. Ensure Service Contractor applies
suitable coatings to the structure and environment. Also ensure
compatibility with previously applied coatings and other
protective methods, such as cathodic protection.
4. Together with the BCCE, inspect coatings
on all high cost steel structures semiannually.
5. Coordinate closely with Maintenance
Engineering to ensure compliance with paragraphs 4a(6)(a) through
4a(6)(i).
6. Use AF Form 1687, Leak/Failure Data
Record, an appropriate and forward to the BCCE.
(e) Water distribution systems corrosion control
craftsman will (OPR: Infrastructure Support Element):
1. Perform leak/failure inspections as
required. Notify the BCCE of leaks and failures in the water
distribution systems.
2. Use AF Form 1687, Leak/Failure Data
Record, for all leaks detected in the water distribution systems
and forward to the BCCE.
3. Coordinate with the water systems and
treatment corrosion control craftsman (Water & Waste) on possible
water distribution leaks.
4. Procure and retain custody of test
equipment necessary for leak detection in the water distribution
system.
(f) POL/JP4 distribution systems corrosion
control craftsman will (OPR: Infrastructure Support Element):
1.
Perform leak/failure inspections as
A-8