UFC 4-021-01
18 DECEMBER 2002
CHAPTER 5
MAINTENANCE CRITERIA
5-1
INTRODUCTION. This chapter was developed on the basis of
recommendations from manufacturers of mass notification systems, as well as
experience with similar computer-based systems.
Maintenance requirements established for each mass notification system must
consider the manufacturers' maintenance recommendations and applicable DOD
maintenance requirements.
5-2
INDIVIDUAL BUILDING MASS NOTIFICATION SYSTEM. See UFC 3-600-
02, Operations and Maintenance: Inspection, Testing, and Maintenance of Fire
Protection Systems, Paragraph 2-2.2, "Fire Detection and Alarm Systems," for
applicable guidance on inspection, testing, and maintenance of engineered protection
features in DOD facilities.
5-3
GIANT VOICE MASS NOTIFICATION SYSTEM. Table 5-1 provides
maintenance information for the Giant Voice system when interfaced or used as a mass
notification system.
Table 5-1. Giant Voice System Maintenance
Component
Tasks
Central control
Weekly
Verify no diagnostic failures indicated.
console
Wireless transceivers
Perform silent activation of entire system.
Perform a test system activation for a
Monthly
particular zone.
Total system
functionality
Verify field components perform as
expected.
Verify that system will operate in the
absence of line power; discontinue line
power to system and verify
functionality.
Central control unit,
Quarterly
Test UPS. See AFPAM 32-1186,
UPS
Valve-Regulated Lead-Acid Batteries
for Stationary Applications, and NFPA
70B, Recommended Practice for
Electrical Equipment Maintenance.