24
2.3
Environmental
2.3.1 In general, an Environmental Baseline Study (EBS) and an
Environmental Assessment (EA), with a finding of no significant
impact (FONSI), must be completed for each AR project.
Preparation of these documents is the responsibility of the RSC, but
the design team must become familiar with any requirements from
the studies which are to be included in the design, such as erosion
control measures.
2.3.2 See Paragraph 2.2.1.3.4 above for environmental permitting
requirements.
Figure 2-3 Site Access
2.4
Site Selection
2.4.1 General Selection and Planning Criteria
and Planning
2.4.1.1 In most cases, the project site will have already been
selected, based on the following characteristics. If the Design
Agency is involved in site selection, the factors below, along with
the budget, are important factors to be considered. For additional
site selection considerations, see Section 2.5, Antiterrorism/Force
Protection.
2.4.1.1.1 A relatively level site, suitable for the parking of military
training vehicles.
UFC 4-171-05