Quality Assurance Section. The quality assurance
section includes those items not covered elsewhere in the general
information or execution parts that are necessary to ensure that
quality work will be obtained from the contractor.
a)
They may include the following:
(1)
Qualifications
(2)
Certifications
(3)
Field sampling
(4)
Regulatory requirements
(5)
Preconstruction conference
b) Qualification or certification statements may be
requested to establish the capabilities of the contractors and
his employees. This is particularly necessary, if capabilities
with high pressures from airless spray or other safety hazards
require special certification. The SSPC Painting Contractor
Certification Program will ensure the capability of completing
the work in a satisfactory manner and time. Additional
certification may be required if asbestos fibers or lead-based
paint complicate the work. It is desirable to include a clause
permitting the contracting officer to procure at any time a
sample of the paint being applied. Local air pollution personnel
usually have this authority.
c) The contractor must be familiar with prevailing
regulations. Material safety data sheets (MSDS) for paints,
solvents, and other materials to be used should also be submitted
and kept available on-site. In addition, coating manufacturer's
technical data sheets should also be on-site and available.
d) A preconstruction conference and site visit of
contracting officer and contractor personnel should be held
before the work begins. At this time, any differences of opinion
or uncertainties should be resolved. Any agreements reached that
affect the specification should be written down and signed by
both parties so that it becomes a part of the contract. Any
differences not resolved may result in costly change orders.
8.3.1.6
Delivery, Storage, Handling, and Disposal. Information
must be provided on acceptable methods of delivery, storage, and
handling. Packaging and shipping procedures must be in
accordance with prevailing regulations. There must also be
suitable arrangements for acceptance and storage of materials on
133