MIL-HDBK-1164
Table 18
Startup Checklist for Vertical Turbine Well Pumps
Inspection
Action
Prestart Inspection
Well
Disinfect according to par. 4.5.2.5.
Pump equipment
Check alignment.
Valve and piping
Check for proper operation. Check for leaks. Set
system
valves so water pumped at startup does not feed into
distribution system until bacteriological quality has
been tested and clearance received.
Pre-lubricate bearings on water-lubricated, line-shaft
pumps with settings of more than 50 feet.
Electrical
Make sure that all electrical connections are correct
connections
and that terminals are tight.
to the manufacturer's instructions.
Startup Inspection
Pump
Start pump. Check immediately for evidence of
malfunction or excessive heat or vibration. Check
operating power input.
Motor
Check for malfunction or excessive heat or vibration.
Check rotation direction of motor. Check water or oil
lubrication system
Observe how quickly motor comes up to operating
speed; check final operation speed.
Check for excessive heat or vibration.