UFC 4-390-01
23 July 2003
Applicant Applies for System Certification
SCA Responds to Application, Provides
Comments and Requests Funding
Requirements
Applicant and SCA Negotiate SOC and
Milestone of Events
Applicant Collects, Organizes, and Submits
Certification Documentation
Reject
Applicant Performs and
SCA Reviews, Approves
Documents Required
and/or Rejects
Corrective Action
Documentation
Corrective action
Applicant Performs and
SCA Performs On-Site
Documents Required
Survey
Corrective Action
Corrective action
Applicant Performs and
SCA observes
Documents Required
Operational
Corrective Action
Demonstration
SCA Issues Letter of Certification and Certificate
of Material and Procedural Adequacy
Sponsor Sustains System Certification
Throughout Tenure in Accordance with SCA
Requirements
Sponsor Requests Continuance of Certification
Prior to Expiration of Tenure
Figure 1
Certification Sequence of Events