UFC 3-260-11FA
25 May 2005
Specification
Item Description
Submittal Date
Reference
First Design Submittal
01321 1.7.3
Construction Network Analysis
Schedule
5 days after Design and
01321 1.7.3
Baseline Network Analysis
Construction Schedule
Schedule
Network Diagrams
acceptance
Tabular Reports
Cash Flow S-Curve
Monthly Intervals
01321 1.7.6
Monthly Network Analysis
Updates
Narrative Report
Tabular Reports
Network Diagrams
Update Meeting Minutes
6-month interval and after
01321 1.7.7
Summary Network Report
Summary Network Diagram
each major schedule
change
Activity ID Report
Total Float Report
Earned Value Report
01321 1.7.8
As-Built Schedule
With last schedule update
01321 1.8
Contract Modification
If needed
01321 1.8.1
Time Impact Analysis
With a proposed contract
change
01321 1.11
3 week look ahead schedule
Weekly
01321 1.12
Weekly coordination meeting
1 day after meeting
minutes
With final design
Draft DD Form 1354
01331 3.1
As needed
Shop Drawings
01331 3.2
01331 3.2
Product Data
As needed
01331 3.2
Samples
As needed