Table 1 (Continued)
Factors for Individual Facilities by Navy Category Code[1]
DEMAND
LOAD
NAVY
FACTOR FACTOR
CODE
DESCRIPTION
(%)
(%)
730
70
Decontamination facility . . . . . . . . . . . . . .75-80
15-2
730
83
Chapel . . . . . . . . . . . . . . . . . . . . . . .65-70
5-25
730
85
Post Office . . . . . . . . . . . . . . . . . . . . .75-80
20-25
740
01
Exchange retail store . . . . . . . . . . . . . . . .65-70
25-32
740
18
Bank . . . . . . . . . . . . . . . . . . . . . . . .75-80
20-25
740
23
Commissary including backup storage . . . . . . . . .55-60
25-30
740
26
Installation restaurant . . . . . . . . . . . . . . .45-75
15-25
740
30
15-20
740
36
Hobby shop, art/crafts . . . . . . . . . . . . . . .30-40
25-30
740
40
Bowling Alley . . . . . . . . . . . . . . . . . . . .70-75
10-15
740
43
Gymnasium . . . . . . . . . . . . . . . . . . . . . .70-75
20-45
740
46
Skating rink . . . . . . . . . . . . . . . . . . . .70-75
10-15
740
50
Field house . . . . . . . . . . . . . . . . . . . . .75-80
7-12
740
53
Indoor swimming pool . . . . . . . . . . . . . . . .55-60
25-50
740
56
Theater . . . . . . . . . . . . . . . . . . . . . . .45-55
8-13
740
60
Commissioned officers' mess, open . . . . . . . . . .55-60
15-20
740
63
Enlisted personnel club . . . . . . . . . . . . . . .55-60
18-23
740
66
Petty officers' mess, open . . . . . . . . . . . . .55-60
18-23
740
70
Mess open, E-7 through E-9 . . . . . . . . . . . . .55-60
15-20
740
76
Library . . . . . . . . . . . . . . . . . . . . . . .75-80
30-35
740
80
Golf club house . . . . . . . . . . . . . . . . . . .75-80
15-20
740
86
Exchange installation warehouse . . . . . . . . . . .58-63
23-28
740
88
Educational services office . . . . . . . . . . . . .70-75
30-35
760
10
Museum/memorial building . . . . . . . . . . . . . .75-80
30-35
800
Utilities and Ground Improvements:
811
10
Electric power plant-diesel . . . . . . . . . . . . .60-65
58-63
811
25
Electric power plant-steam . . . . . . . . . . . . .60-65
58-63
811
45
Electric power plant-gas turbine . . . . . . . . . .60-65
58-63
811
60
Standby generator plant . . . . . . . . . . . . . . .75-80
5-10
812
20
Street lighting . . . . . . . . . . . . . . . . . . .95-..
46-..
812
40
Perimeter/security lighting . . . . . . . . . . . . .80-85
22-27
813
20
Substation, more than 499 KV . . . . . . . . . . . .25-30
20-25
821
12
Fossil fuel heating plant - medium . . . . . . . . .55-60
30-60
821
22
Fossil fuel heating plant - large . . . . . . . . . .55-60
30-60
821
50
Non-nuclear steam plant . . . . . . . . . . . . . . .50-55
30-40
826
20
Chilled water plant 25/100 tons . . . . . . . . . . .60-70
25-30
827
20
distribution system - medium (25/100 tons) . . . . 60-70
25-30
831 10
Combination sewage and industrial waste
treatment plant . . . . . . . . . . . . . . . . . 60-70
15-20
832
30
Sewage-industrial waste pumping station . . . . . . .55-60
30-35
833
22
Incinerator building and incinerator . . . . . . . .55-60
15-20
841
10
Water treatment facilities . . . . . . . . . . . . .60-80
15-25
841
50
15-25
1Demand factors include allowance for system loss.
7