UFC 4-211-01N
25 October 2004
change keys for individual doors. The building should have a grand master key
system.
3-19.6
Windows And Glazing (Interior). Choose single pane glass set in
metal wrap-around frames. Choose wire or tempered type as required by code
based on the opening rating. Use laminated glass for windows exposed by the
hangar bay. Thermal insulated glass should have a laminated glass pane on the
inside (occupied side) of the window assembly.
For openings in the wall between the Hangar and Maintenance
Control, provide fire-rated steel windows. Glazing should be wire glass or fire
rated type.
For windows in 2-hour rated walls, provide a fire shutter or 2hr. fire-
rated windows.
3-20
FINISHES. Coordinate finishes with the activity based on
maintainability and appropriateness for the application. Long-term costs should
Floors.
Shops, tool room, etc Concrete with sealer or Epoxy
Administrative spaces Resilient tile
Locker rooms Ceramic tile
Toilets Ceramic tile
Showers Ceramic tile
Corridors Resilient tile or Epoxy
Entry Lobby Ceramic Tile or other durable finish.
3-20.1
Bases.
Shops, Administrative spaces, corridors, and spaces with resilient
flooring or carpet Resilient
Spaces with Ceramic tile walls and floors Ceramic
3-20.2
Walls. Paint all walls except ceramic tile walls.
3-20.3
Ceilings.
Administrative Spaces - Suspended Acoustical
18