208
G.1
Continued
G.1.3.5 Recording room 7.5 sq m (80 sf)
G.1.3.6 Library 15 sq m (160 sf)
G.1.3.7 Main rehearsal room 146 sq m (1575 sf)
G.1.4 For the main rehearsal room provide a two-tier riser stage. The first
tier should have a 200 mm (8 in) riser and a 1525 mm (5 ft) minimum tread.
The second tier should have an equal riser.
G.1.5 Provide storage shelving for sheet music, catalogs, records, tapes and
CDs in the library.
G.1.6 Space Design Information: Space design should be similar to that for
administrative spaces. Verify specific finish, furniture, equipment, power,
lighting, communications and other needs with Tenants. Tenants will furnish
audio equipment, music stands, and similar items. Furniture will be part of
the designer's furniture design and package.
G.1.6.1 Provide quiet air distribution to reduce ambient sound level.
Design sound attenuation for ductwork between band room and
adjacent spaces.
G.1.6.2 In instrument cleaning room, consider providing a large,
polyethylene sink with a gooseneck faucet in a cabinet with drawers
for washing band instruments.
G1.6.3 Lighting should be 50 fc.
G1.6.4 The ceiling in the rehearsal rooms should be a minimum of
G1.6.5 Rehearsal and practice rooms doors will be sound control
doors with acoustical seals and an automatic bottom sweep.
UFC 4-171-05