The Alpha Designation that follows the first six digits of the contract
number is deleted.
For example, construction contract number N62470-03-B-3209 corresponds to
specifications number 05-03-3209 for NAVFAC Atlantic.
5-5.2.5
Division 01 Sections.
Tailor, as applicable, the UFGS Division 01 Sections describing the general project
requirements for use in the project. Include any additional section of a general
requirement nature rather than a technical nature in Division 01.
5-5.3
Use Of Specsintact.
Prepare Design-Bid-Build project specifications utilizing Construction Specifications
Institute (CSI) format and utilizing the SpecsIntact application.
5-6
DESIGN-BUILD PROJECT SPECIFICATIONS.
For Design-Build RFP use UFGS 01331, edited for a specific project's requirements that
gives specific guidance on the preparation of Design-Build project specifications. UFGS
01331 is available for download and subsequent editing from the NAVFAC Design-Build
5-6.1
Design-Build Request For Proposal Preparation
Guidance on preparing the RFP for design-build projects is available on
The site is intended to (1) familiarize those new to the Design-Build
process with the RFP format and typical RFP specification sections and
(2) allow those preparing a Design-Build RFP to download the electronic
documents. The Design-Build RFP Web Site is organized using tabs for
the major sections and organization structures for the various categories
of information within each tabbed section. The RFP must include all six
RFP Parts indicated below unless they are not applicable to the project.
The typical facility project will have information in every RFP Part, with the
possible exception of RFP Part Five, "Prescriptive Specifications".