UFC 1-300-09N
25 May 2005
Part One includes the Proposal Form and Documents and specifies tha
contractual requirements.
Part Two contains the General Requirements Specification Sections.
Part Three contains the Project Program for the project.
Part Four contains the Performance Technical Specifications.
Part Five contains any Prescriptive Specifications required for the design-
build RFP.
Part Six is for Attachments (e.g., Boring Logs).
5-6.1.1
Part One: Proposal Forms and Documents.
Part One, Proposal Forms and Documents, contains the contract documents that are
prepared by the Contract Specialist using the standard design-build template in the
Standard Procurement System - Procurement Desktop Defense module (SPS-PDD)
and included in the RFP.
5-6.1.2
Part Two: General Requirements.
Part Two, General Requirements, contains the Division 01 specifications. Most of these
sections are available on the UFGS web site. The design-build specific sections are
only available on the Design-Build Master web site.
5-6.1.3
Part Three: Project Program.
Part Three is dedicated to the Project Program. A project program is the documentation
of the operational, functional, and space planning requirements from an architectural
5-6.1.4
Part Four: Performance Technical Specifications.
Part Four, Performance Technical Specifications (PTS), contains the performance
technical sections that define the performance and quality of the building elements that
are required by the Project Program. The performance technical sections are arranged
by the Uniformat II/WBS building element classification system and tie directly to the
numbering system used in the Project Program. Within the PTS, the information on
particular subsystems is referenced through Level Three and Level Four of the
Uniformat II/WBS. As with the UFGS, the PTS are editable by the RFP preparer to
reflect the characteristics of a particular project. Notes in the text provide guidance on
the decision making process for editing.
5-6.1.5
Part Five: Prescriptive Specifications.
Part Five, Prescriptive Specifications, contains edited Unified Facility Guide
Specifications (UFGS) (other than those incorporated into the PTS) which are part of
the Design-Build RFP. The Design-Build RFP preparer should attach the full text edited
version of these UFGS rather than referencing a location for view or download of the