UFC 1-300-09N
25 May 2005
6-2.1.4
Design Development.
Design Development submissions are at design stages that vary from project to project.
The submission requirements for a project will be outlined in the A/E Contract or in-
house Scope of Work. Minimum Design Development submission requirements are
outlined in the respective design discipline sections of Chapter 8 and 9.
6-2.1.5
Final Design.
The final design submission is the complete project design document prepared for
release for bidding. The final submission is inclusive of all design drawings and
specifications, as well as an updated and complete Basis of Design. Make Final
Submission electronic deliverables in accordance with UFC 1-300-10N.
Before drawings and specifications are submitted for formal approval, the individuals
directly responsible for the accuracy and sufficiency of the data included therein must
sign the drawings and specifications in accordance with UFC 1-300-10N.
6-2.1.6
Design Submissions after Final Design.
Design submissions made after final design include A/E and Government responses to
contractor requests for clarification (RFC) and requests for information (RFI), as well as
change order documents, and as-built drawings. Submissions may include sketches,
additions and/or corrections to drawings and specifications. Make changes after the
Final Submission in accordance with Chapter 10, "Changes to the Final Submission".
As-built documents are submitted by the contractor at the completion of the construction
phase and reflect all changes made during construction. The record documents include
all of those project design documents that constitute the Final Submission, edited to
include the changes.
6-2.1.7
Cost Estimates.
Submit the contract cost estimate electronically with each submittal. Do not submit the
cost estimate on the project CD when provided. Make all cost estimating submissions
in accordance with the NAVFAC Cost Engineering Policy and Procedures
6-3
ALL CONSTRUCTION SUBMISSIONS.
6-3.1
Construction Submissions.
The submittal procedures between NAVFACENGCOM and the Contractor are included
in the contract documents; procedures for Quality Control (QC) are included in UFGS
Section 01450N, Construction Quality Control, 01451N, Design and Construction
Quality Control and 01455N, Quality Control (QC) - Minor Construction, depending on
the type of project. Procedures within NAVFACENGCOM follow:
22