UFC 1-300-09N
25 May 2005
CHAPTER 8 DESIGN-BID-BUILD SUBMITTAL REQUIREMENTS
NOTE: All electronic submittals must be in accordance with UFC 1-300-10N. As a
minimum all final submittals must be in electronic format. The project scope of work
must define any other submittals required in electronic format.
8-1
ARCHITECTURAL SUBMITTALS.
8-1.1
Concept Design Submittals.
The Concept Design Submittal is intended to convey the extent of the work in a
preliminary conceptual manner. Drawings are approximately 10% to 15% complete at
this stage. This submittal must include, as a minimum:
8-1.1.1
Basis of Design.
Submit a preliminary version of the Basis of Design addressing all items defined
elsewhere in this guide.
8-1.1.2
Drawings.
As a minimum, provide the following drawings:
Floor Plans Provide all floor plans, new and demolition, indicating room
names and basic dimensions.
Building Elevations Provide all building elevations indicating all exterior
materials.
Building Section Indicate heights of critical building elements.
8-1.2
Design Development Submittals.
The Design Development Submittal is intended to convey the complete extent of the
work in a preliminary manner. The drawings are typically about 35% to 50% complete
at this stage. This submittal must include, as a minimum:
8-1.2.1
Basis of Design.
Submit a complete Basis of Design addressing all items defined in UFC 3-100-10N,
Design: General Architectural Requirements and UFC 1-200-01, Design: General
Building requirements.
8-1.2.2
Drawings.
As a minimum, provide the following drawings:
Floor Plans Provide all floor plans, new and demolition, indicating room
names and dimensions.
28