UFC 1-300-09N
25 May 2005
Provide complete specifications in accordance with Chapter 5.
8-2.4.3
Cost Estimate.
Submit complete updated cost estimate.
8-2.4.4
Annotated Review Comments.
Provide written responses to all government review comments.
8-3
STRUCTURAL SUBMITTALS.
8-3.1
Design Development Submittals.
8-3.1.1
Basis of Design.
Submit a complete Basis of Design addressing all items defined in UFC 3-300-10N,
Design: General Structural Requirements.
8-3.1.2
Drawings.
As a minimum, submit the following drawings developed in sufficient detail to support
the items outlined in the Basis of Design:
Foundation Plans - Include for all structures, showing dimensions,
arrangements, elevations, locations referred to a column line grid system,
type of foundation and foundation obstructions. Include the layout of all
slabs, footings, piers, grade beams, piles, etc., showing all foundation
features of the design.
Framing Plans Include a framing plan for each structural level of the
facility, showing dimensions, elevations, and column locations and
numbering referenced to a column line grid system, and overall sizes of
major members and components. Show the layout of beams, joists,
stringers, etc.
Structural Details Show typical details of construction, indicating the
connection and relationship between major components of the structural
system.
Structural Elevations Show general sizes, location and arrangement of
all significant features of the vertical framing system, including columns,
walls, beams, etc.
8-3.1.3
Outline Specifications.
Provide preliminary outline specifications in accordance with Chapter 5.
8-3.1.4
Calculations.
33