UFC 1-300-09N
25 May 2005
HVAC Floor Plan. Show equipment locations, one or two-line duct layout
and preliminary piping runs.
Mechanical Room Plan. Show major equipment and maintenance access
space. Provide section view(s) to clarify layout and supports.
8-4.1.3
Calculations.
Provide the following calculations, as a minimum, accompanying the Design
Development submittal:
8-4.1.4
Energy Analysis.
Provide a bound copy of the computerized energy analysis that includes input and
output data in their entirety.
8-4.1.5
Life Cycle Cost Analysis.
Submit the computerized LCC analysis utilizing the latest edition of the NIST Building
Life-Cycle Cost Program.
8-4.1.6
Provide a bound copy of the computerized load calculations with input and output data
in their entirety.
8-4.1.7
ASHRAE 90.1 Compliance Calculations.
Submit calculations and compliance forms indicated in the Basis of Design.
8-4.2
Pre-Final Design Submittals.
8-4.2.1
Drawings.
Plumbing and mechanical drawings must be complete to the extent that they may be
released for bid as submitted.
8-4.2.2
Calculations.
Submit all calculations to support the plumbing and mechanical systems and the major
equipment comprising those systems. Update the 35% energy analysis with the
equipment efficiencies scheduled on the drawings.
8-4.2.3
Basis of Design.
Submit revised basis of design.
36