UFC 1-300-09N
25 May 2005
Outline Specifications.
Electrical Design Check List.
8-5.2
Design Development Submittals.
a) Submittal must include all requirements of the previous submittal plus additional
detail to bring them to the required completion percentage.
Legend and Abbreviations
Existing Site and Demolition Plan: Plans must be developed to
approximately 50 percent completion.
Site Plan: Plan must be developed to approximately 50 percent
completion.
Lighting Plan(s): Plans must show a building's full floor plan (first, second,
etc.) with the layout and type of fixtures to be used. No wiring or circuits
required. Scale will be 1:100 (1/8" = 1'-0") minimum.
Power Plan(s): Plans must show a building's full floor plan (first, second,
control centers, transformers and any other major equipment. No wiring
or circuits required. Scale will be 1:100 (1/8" = 1'-0") minimum.
Lightning Protection Plan: No details required.
Cathodic Protection Plan: Include the location of soil resistivity
measurements. No details required.
Special Systems Plans: Show location of devices (e.g., telephone, IDS,
others as required).
Single Line Diagram: Plan must be developed to approximately 50
percent completion showing all panels, switchboards, motor control
centers, transformers and other major electrical loads such as motors,
chillers, etc.
Additional Plans/Risers
Updated Design Analysis to substantiate design level shown.
b) Submit Design Calculations to substantiate design level shown including:
Lighting: Interior and Exterior Foot-candles.
Load Analysis
Service size
Feeder size
Larger special circuit sizes
c) Outline Specifications
d) Response to Previous Submittal Review Comments
e) Electrical Design Checklist
38