UFC 1-300-09N
25 May 2005
Provide written responses to all government review comments.
8-3.3
Final Design Submittals.
The intent of the Final Submittal is to provide a complete and final set of contract
documents ready for bidding by the government, or in the case of Design-Build, ready
for construction by the contractor. All government comments must have been
addressed. The following is the minimum required of a Final Submittal:
8-3.3.1
Drawings.
Provide complete construction drawings.
8-3.3.2
Specifications.
Provide complete specifications in accordance with Chapter 5.
8-3.3.3
Cost Estimate.
Submit complete updated cost estimate.
8-3.3.4
Calculations.
Calculations must be revised as required to reflect resolution of all previous government
review comments.
8-3.3.5
Annotated Review Comments.
Provide written responses to all government review comments.
8-4
MECHANICAL SUBMITTALS
8-4.1
Design Development Submittals.
8-4.1.1
Basis of Design.
Provide as indicated in UFC 3-400-10N, Design: General Mechanical Requirements.
8-4.1.2
Drawings.
Provide the following sheets, as a minimum, for the design development submittal:
Plumbing Floor Plan. Show plumbing fixtures, floor drains and equipment
locations.
Site Plan. Show connection to base steam distribution, location of
propane and oil tanks, layout of ground coupled heat pump well fields, etc.
35