UFC 1-300-09N
25 May 2005
Provide preliminary outline specifications in accordance with Chapter 5.
8-2.2.4
Cost Estimate.
Provide preliminary cost estimate. See NAVFAC Cost Engineering Policy and
8-2.3
Pre-Final Design Submittals.
The intent of the Pre-Final submittal is to provide a complete set of drawings and
specifications. Specifications may be in an edited, or redlined format. The following are
the minimum requirements of a Pre-Final submittal:
8-2.3.1
Basis of Design.
Resubmit the Basis of Design. Update information as necessary.
8-2.3.2
Drawings.
Provide a complete set of construction documents organized by discipline in
accordance with UFC 3-200-10N.
8-2.3.3
Specifications.
Provide complete specifications in accordance with Chapter 5.
8-2.3.4
Cost Estimate.
Submit complete detailed cost estimate. See NAVFAC Cost Engineering Policy and
8-2.3.5
Annotated Review Comments.
Provide written responses to all government review comments.
8-2.4
Final Design Submittals.
The intent of the Final Submittal is to provide a COMPLETE and FINAL set of contract
documents ready for bidding by the government. All government comments must have
been addressed. The following is the minimum required of a Final Submittal:
8-2.4.1
Drawings.
Provide a complete set of construction drawings organized by discipline in accordance
with this UFC.
8-2.4.2
Specifications.
32