UFC 1-300-09N
25 May 2005
Building Elevations Provide all building elevations indicating all exterior
materials.
Roof Plan Provide a plan of all roof areas, indicating direction of slope
Building Section Indicate heights.
Typical Wall Sections Provide sufficient wall section(s) to indicate all
materials and different conditions.
Finish Schedule Indicate all proposed finishes
Furniture Plan.
8-1.2.3
Specifications.
Provide preliminary outline specifications in accordance with Chapter 5.
8-1.2.4
Cost Estimate.
Provide Preliminary cost estimate. See NAVFAC Cost Engineering Policy and
8-1.2.5
Color Boards.
Provide separate interior and exterior color boards indicating all proposed material and
color selections.
8-1.3
Pre-Final Design Submittals.
The intent of the Pre-Final submittal is to provide a complete set of drawings and
specifications. Specifications may be in an edited, or redlined format. The following are
the minimum requirements of a Pre-Final submittal:
8-1.3.1
Basis of Design.
Resubmit the Basis of Design. Update information as necessary.
8-1.3.2
Drawings.
Provide complete construction drawings as described in UFC 3-100-10N.
8-1.3.3
Specifications.
Provide complete specifications in accordance with Chapter 5.
8-1.3.4
Cost Estimate.
Submit complete detailed cost estimate. See NAVFAC Cost Engineering Policy and
29