UFC 1-300-09N
25 May 2005
8-1.3.5
Color Boards.
Provide separate updated interior and exterior color boards indicating all proposed
material and color selections.
8-1.3.6
Annotated Review Comments.
Provide written responses to all government review comments.
8-1.4
Final Design Submittals.
The intent of the Final Submittal is to provide a complete and final set of contract
documents ready for bidding by the government, or in the case of Design-Build, ready
for construction by the contractor. All government comments must have been
addressed. The following is the minimum required of a Final Submittal:
8-1.4.1
Basis of Design.
Resubmit the Basis of Design. Update information as necessary.
8-1.4.2
Drawings.
Provide complete construction drawings.
8-1.4.3
Specifications.
Provide complete specifications in accordance with Chapter 5.
8-1.4.4
Cost Estimate.
Submit complete updated cost estimate.
8-1.4.5
Color Documentation Binders.
Provide separate interior and exterior color documentation binders indicating all
proposed material and color selections.
8-1.4.6
Annotated Review Comments.
Provide written responses to all government review comments.
30