Calculations must be complete in sufficient detail to support the items outlined in the
Basis of Design and indicated on the drawings.
8-3.1.5
Cost Estimate.
Submit an estimate of probable cost, with a level of detail appropriate for the status of
the design at this stage. See NAVFAC Cost Engineering Policy and Procedures
8-3.2
Pre-Final Design Submittals.
The intent of the Pre-Final submittal is to provide a complete set of drawings and
specifications. Specifications may be in an edited, or redlined format. The following are
the minimum required of a Pre-Final submittal:
8-3.2.1
Basis of Design.
Supplement the Basis of Design discussions as necessary and respond to reflect
previous government review comments. Resubmission of corrected Basis of Design is
not required.
8-3.2.2
Drawings.
Drawings must be 100% complete, minus signatures, and modified to reflect the
responses to previous review comments. Prepare drawings with sufficient detail that
structural decisions and choices need not be made in the field. Address all construction
conditions in the construction documents, including details that apply to specific
conditions, complete schedules, identification of all members, dimensions, connection
details, etc.
8-3.2.3
Specifications.
Modify specifications to reflect the responses to previous review comments. They must
be 100% complete. Provide complete specifications in accordance with Chapter 5.
8-3.2.4
Calculations.
Revise calculations as required to reflect resolution of all previous government review
comments. At this stage, the analysis must be 100% complete.
8-3.2.5
Cost Estimate.
Submit an estimate of probable cost, including all of the items shown on the drawings
and specifications.
8-3.2.6
Annotated Review Comments.