UFC 1-300-09N
25 May 2005
8-4.3
Final Design Submittals.
8-4.3.1
Drawings.
Submit the final plumbing and mechanical drawings in accordance with UFC 3-400-10N.
8-4.3.2
Calculations.
Submit the final plumbing and mechanical calculations, revised and updated, in
accordance with UFC 3-400-10N.
8-4.3.3
Basis of Design.
Submit final basis of design, revised and updated, in accordance with UFC 3-400-10N.
8-5
ELECTRICAL SUBMITTALS.
Listed below are design submittal requirements for specific levels of design completion.
Not all submittals listed may be required. The Statement of Work (SOW) or RFP will
indicate the number of and required completion percentage (e.g., 35%, 100%, Final) of
all submittal requirements. Only those submittals listed in the SOW are required and
each required submittal must follow the guidelines indicated below.
8-5.1
Concept Design Submittals.
The Concept Design Submittal need not provide extensive details but must be complete
enough to thoroughly express the Designer's intentions and include the following:
Existing Site and Demolition Plan: Plans must include all existing site
information such as buildings, pavements and utilities. All electrical
demolition must be shown and indicated by legend. Demolished features
must not be shown on subsequent drawings. Indicate existing exterior
power and telecommunications distribution to a point of connection.
Site Plan: Plan must show new and remaining aboveground and
underground electrical lines and equipment. Show other utilities in
proximity to electrical utilities. Information on existing conditions must be
complete and field checked. Show proposed Power and
Telecommunications cabling and routing.
Single Line Diagram (Not a Riser) including Pad mounted transformer or
substation with primary and secondary protective devices: Show
Secondary feeders to major items of equipment.
Preliminary floor plans with dedicated space clearly identified for electrical
and telecommunications rooms: Show proposed locations for large
equipment such as HVAC connections, Switchgear or Switchboards, and
400 Hertz equipment, etc.
Design Analysis including Preliminary load calculations for Utility
connections.
37