UFC 1-300-09N
25 May 2005
8-5.3
Pre-Final Design Submittals.
a) Submittal must include all requirements of the previous submittal plus additional
detail to bring them to the specified completion percentage. Drawings and
specifications must be substantially complete at this stage and require only minor
corrections if any.
Legend and Abbreviations
Existing Site and Demolition Plan
Lighting Plans and Details
Power Plans and Details
Power - Single Line Diagram
Telephone Riser Diagram
Intercommunication Riser Diagram
Fire Alarm Riser Diagram: Include only when separate Fire Protection
Drawings are not included in the design.
Other Riser Diagrams for Television, Security, Etc.
Panel Schedules
Switchboards and Motor Control Center Schedules
Lighting Fixture Details
b) Updated Design Analysis to substantiate design level shown
c) Sequence of Construction when applicable
d) Updated Calculations from previous submittal to substantiate design level shown
including the following as applicable.
Short Circuit
Voltage Drop
Lighting
Load Analysis
Motor Starting/Flicker Analysis
Sag, Tension, and Guying Analysis
Manhole Design Calculations
Cable Pulling Tension Calculations
Cathodic Protection Calculations
CATV Network Loss Calculations
e) Redlined Specifications
f) Design must be free of conflicts between the contract drawings and the specifications.
g) Response to Previous Submittal Review Comments
39