UFC 3-580-10
14 July 2004
Including changes 12 April 2005
3-2.6
Public Works. In addition to the ROICC responsibilities for all
projects as identified above, Public Works will provide support including:
Utility connection and interface, design review and coordination,
and support on utility outages and connections.
Input to the Site Concurrence Memorandum (SCM) concerning
utilities and equipment maintenance and coordination with the
NMCI Contractor.
Other support as requested.
Public Works is defined as Public Works Centers (PWC) (when site
is covered by PWC area of responsibility and when funded by regional
commanders or major claimants) or as Public Works Departments (PWD) /
Facilities Management Departments (FMD) / Public Works Offices (PWO).
NOTE: Based on current reorganization efforts, many of the support
responsibilities of NAVFACENGCOM, ROICC and Public Works will actually be
coordinated through the Facilities Engineering Commands (FECs.)
3-2.7
U. S. Marine Corps (USMC) Additional Requirements. The
Communications Officer on USMC bases, called the G6, should be involved in all
phases of the pre-construction. While PWD issues the excavation permits, the
G6 locates, installs and removes cables on base, and develops building EFs and
TRs. The G6 will provide support including:
Input to the Site Concurrence Memorandum (SCM) concerning
utilities and equipment maintenance and coordination with NMCI
Contractor.
3-3
PHASE 1 PREPARATION. The initial introduction meetings
between the NMCI Contractor and the chain of command are conducted prior to
this preparation phase. As a part of these preparations, the NMCI Contractor
sends a letter to the base Commanding Officer (CO) stating that seats have been
requested on a delivery order. The NMCI Contractor BAN / LAN team will arrive
on site and begin collecting the data needed for the conversion. While the NMCI
Contractor begins to mobilize, the CO should instruct the Public Works
Department or the ROICC to make available to the NMCI Contractor Site
Manager, existing drawings and diagrams detailing electrical distribution and
communications cabling throughout the base. These documents should be in
Computer Aided Design, Drafting (CADD) format where available.
3-3.1
BAN / LAN Implementation Team. A BAN / LAN team is
responsible for identifying and dedicating infrastructure components to the NMCI
Contractor including available conduits, fiber, and copper cable. This
20