1.5.2.6 Identifying the applicable codes and regulations, and ensuring
that the design is in compliance with them.
1.5.2.7 Preparing cost estimates, and ensuring that the design will provide a
fully functional facility within the project construction cost limit (CCL).
Optional bid items may be required to ensure that a base bid within the
construction cost limit can be achieved. Any such options must be planned
such that the facility is complete and usable without their inclusion.
1.5.2.8 Preparing a draft of DD Form 1354, Transfer and Acceptance of
Military Real Property.
Figure 1-4 ARRTC
1.5.2.9 Preparing any surveys and/or geotechnical, environmental,
VOQ, Ft. McCoy,
sustainable design or other investigations identified in the project Scope of
Wisconsin
Work.
1.5.2.10 Developing design analyses, calculations, and other information
that supports and explains the project design.
1.5.2.11 Identifying issues that will deserve special attention during project
construction.
1.5.2.12 Preparing a draft of specification Section 00800 for the use of the
constructing entity, and reviewing and commenting on the remainder of the
"front-end" specifications.
1.5.2.13 Complete coordination of
A/E discipline
interfaces, and checking
for architectural, structural, HVAC, electrical, plumbing and fire protection
conflicts.
1.5.2.14 Preparing a submittal register for inclusion in the specifications,
coordinated with the construction entity.
1.5.3 The AR Support Installation is responsible for the following:
1.5.3.1 Providing the Design Agency with as-built drawings of existing
construction.
1.5.3.2 For alteration projects, providing a copy of all outstanding
maintenance and repair work orders.
1.5.3.3 Providing a copy of the current 416th Engineering Command Full
Facility Assessment.
1.5.3.4 Providing a condition survey for any existing facilities affected by the
proposed work, along with a list of any red or amber conditions noted in
the Installation Status Report.