UFC 1-300-09N
25 May 2005
9-6.3
Final Design Submittals.
9-6.3.1
Drawings.
Provide all drawings required to meet the intended design approaches for the project.
As a minimum, provide all noted drawings in UFC 3-600-10N.
9-6.3.2
Specifications.
Specifications are not necessary. Provide manufacturer's data sheets for the
suppression systems, detection and alarm systems, firestopping, spray-applied
fireproofing.
9-6.4
Additional Overseas Submittals Requirements.
Host Nation Life Safety and Building Code analysis.
Comparisons with NFPA Codes and UFC 1-200-01
9-7
ENVIRONMENTAL SUBMITTALS.
Environmental submittals vary with the location and type of project. Consult with the
local command environmental office regarding the specific environmental submittals
necessary for the specific project.
57