UFC 1-300-09N
25 May 2005
Design Analysis including Preliminary load calculations for Utility
connections
Outline Specifications
Electrical Design Check List
Sustainable design validation/certification information required in UFGS
01331 of the project RFP
9-5.2
Design Development Submittals.
a) Submittal must include all requirements of the previous submittal plus additional
detail to bring them to the required completion percentage.
b) Legend and Abbreviations
c) Existing Site and Demolition Plan: Plans must be developed to approximately 50
percent completion.
d) Site Plan: Plan must be developed to approximately 50 percent completion.
e) Lighting Plan(s): Show a building's full floor plan (first, second, etc.) with the layout
and type of fixtures to be used. No wiring or circuits required. Scale must be 1:100
(1/8" = 1'-0") minimum.
f) Power Plan(s): Show a building's full floor plan (first, second, etc.) with the location of
other major equipment. No wiring or circuits required. Scale must be 1:100 (1/8" = 1'-
0") minimum.
g) Lightning Protection Plan: No details required.
h) Cathodic Protection Plan: Include the location of soil resistivity measurements. No
details required.
i) Special Systems Plans: Show location of devices (e.g., telephone, IDS, others as
required).
j) Single Line Diagram: Plan must be developed to approximately 50 percent
completion showing all panels, switchboards, motor control centers, transformers and
other major electrical loads such as motors, chillers, etc.
k) Additional Plans/Risers
l) Updated Design Analysis to substantiate design level shown.
m) Submit Design Calculations to substantiate design level shown including:
Lighting: Interior and Exterior Foot-candles.
53