UFC 1-300-09N
25 May 2005
Structural Elevations Show general sizes, location and arrangement of
all significant features of the vertical framing system, including columns, walls,
beams, etc.
9-3.1.3
Outline Specifications.
Provide preliminary outline specifications in accordance with Chapter 5.
9-3.1.4
Calculations.
Calculations must be complete and in sufficient detail to support the items outlined in
the Basis of Design and indicated on the drawings.
9-3.1.5
Cost Estimate.
Submit an estimate of probable cost, with a level of detail appropriate for the status of
the design at this stage. See the cost estimating design guide.
9-3.2
Pre-Final Design Submittals.
The intent of the Pre-Final submittal is to provide a complete set of drawings and
specifications. Specifications may be in an edited, or redlined format. The following are
the minimum required of a Pre-Final submittal:
9-3.2.1
Basis of Design.
Supplement the Basis of Design discussions as necessary and respond to reflect
previous government review comments. Resubmission of corrected Basis of Design is
not required.
9-3.2.2
Drawings.
Drawings must be Pre-Final complete, minus signatures, and modified to reflect the
responses to previous review comments. Prepare drawings with sufficient detail that
structural decisions and choices need not be made in the field. Fully address all
construction conditions in the construction documents, including details that apply to
specific conditions, complete schedules, identification of all members, dimensions,
connection details, etc.
9-3.2.3
Specifications.
Modify specifications to reflect the responses to previous review comments, and ensure
they are 100% complete. Provide complete specifications in accordance with Chapter
5.
9-3.2.4
Calculations.
49