UFC 1-300-09N
25 May 2005
9-2.4.1
Basis of Design.
Resubmit the Basis of Design. Update information as necessary, including sustainable
design validation/certification information required in UFGS 01331 of the project RFP.
9-2.4.2
Drawings.
Provide a complete set of construction drawings organized by discipline in accordance
with UFC 3-200-10N.
9-2.4.3
Specifications.
Provide complete specifications in accordance with Chapter 5.
9-2.4.4
Cost Estimate.
Submit complete updated cost estimate.
9-2.4.5
Annotated Review Comments.
Provide written responses to all government review comments.
9-3
STRUCTURAL SUBMITTALS.
9-3.1
Design Development Submittals.
9-3.1.1
Basis of Design.
Submit a complete Basis of Design addressing all items defined elsewhere in this guide.
9-3.1.2
Drawings.
As a minimum, submit the following drawings developed in sufficient detail to support
the items outlined in the Basis of Design:
Foundation Plans - Include for all structures, showing dimensions,
arrangements, elevations, locations referred to a column line grid system,
type of foundation and foundation obstructions. Include the layout of all slabs,
footings, piers, grade beams, piles, etc., showing all foundation features of
the design.
Framing Plans Include a framing plan for each structural level of the
facility, showing dimensions, elevations, and column locations and numbering
referenced to a column line grid system, and overall sizes of major members
and components. Show the layout of beams, joists, stringers, etc.
Structural Details Show typical details of construction, indicating the
connection and relationship between major components of the structural
system.
48