UFC 1-300-09N
25 May 2005
Revise calculations as required to reflect resolution of all previous government review
comments. At this stage, the analysis must be 100% complete.
9-3.2.5
Cost Estimate.
Submit an estimate of probable cost, including all of the items shown on the drawings
and specifications.
9-3.2.6
Annotated Review Comments.
Provide written responses to all government review comments.
9-3.3
Final Design Submittals.
The intent of the Final Submittal is to provide a complete and final set of contract
documents ready for bidding by the government, or in the case of Design-Build, ready
for construction by the contractor. All government comments must have been
addressed. The following is the minimum required of a Final Submittal:
9-3.3.1
Drawings.
Provide complete construction drawings.
9-3.3.2
Specifications.
Provide complete specifications in accordance with Chapter 5.
9-3.3.3
Cost Estimate.
Submit complete updated cost estimate.
9-3.3.4
Calculations.
Revise calculations as required to reflect resolution of all previous government review
comments.
9-3.3.5
Annotated Review Comments.
Provide written responses to all government review comments.
9-4
Mechanical Submittals.
9-4.1
Design Development Submittals.
9-4.1.1
Basis of Design.
Provide as indicated in UFC 3-400-10N.