CIVIL, GEOTECHNICAL AND LANDSCAPE SUBMITTALS.
The following submittals are typically required for Design-Build projects. Refer to the
particular RFP for the exact submittal requirements for each project.
9-2.1
Concept Design Submittals.
The Concept Design Submittal is intended to convey the extent of the work in a
preliminary conceptual manner. Drawings are approximately 10% to 15% complete at
this stage. This submittal must include, as a minimum:
9-2.1.1
Basis of Design.
Submit a preliminary version of the Basis of Design addressing all items defined
elsewhere in this guide and UFC 3-200-10N.
9-2.1.2
Drawings.
As a minimum, provide a conceptual site plan, indicating above and below grade utility
lines, vehicular and pedestrian circulation paths, buildings, parking, paved areas,
preliminary landscape architectural concept, and existing site features to remain.
9-2.2
Design Development Submittals.
The Design Development Submittal is intended to convey the complete extent of the
work in a preliminary manner. The drawings are typically 35% to 50% complete at this
stage. This submittal must include, as a minimum:
9-2.2.1
Basis of Design.
Submit a complete Basis of Design addressing all items indicated in UFC 3-200-10N.
Update sustainable design validation/certification information required in UFGS 01331
of the project RFP.
9-2.2.2
Drawings.
As a minimum, provide the following drawings:
Legend and Notes
Existing Conditions
Utility Plan
Layout Plan for Roads and Parking
Landscape Drawings in sufficient detail to clearly identify the following
items:
Locations of all facilities (buildings, parking areas, roads, existing
vegetation noted for preservation, etc.)
New plantings of trees, shrubs and ground covers